2018 Project Status Update

Posted in Press Releases

AVCP Regional Housing Authority

 

2018 New Housing Construction (As of Oct 2018)

VILLAGE

NO/UNITS

STATUS

Kalskag

2

Project started in 2018

Platinum

1

Project started in 2018

Atmauluak (Title VI)

2

Project complete. Moved-in October 2018

Mertarvik

2

Continuation from 2017. 3 units are complete. 1unit scheduled to be complete 2019. Projected move-ins in 2019.

Quinhagak (ICDBG)

1

Project complete. Move-in soon.

Alakanuk

2

Project will begin in 2019

Chevak

2

Project will begin in 2019

Eek

2

Project will begin in 2019

Nunapitchuk

2

Project will begin in 2019

Stony River

1

Project will begin in 2019

 

The communities with projects to begin in 2019 are waiting for piling to be installed. The installation should begin starting in November 2018 with the actual construction to begin in summer of 2019.

 

 

2018 Modernization, Weatherization and Special Project (As of Oct 2018)

 

 

 

MODERNIZATION

 

VILLAGE

NO/UNITS

SCOPE

STATUS

Nightmute

7

Boiler Service and Woodstove

Project Complete

Kwigillingok

20

Boilers and Repairs

Project Started August 16.

Russian Mission

20

HRV Repair and Woodstoves

Project will started after Kwig project.

Pilot Station

12

Boilers and Repairs

Project Complete

Atmautluak (Title VI)

2

Home Renovations

Project Started but on hold for colder weather.

 

$520,797.19 has been paid in wages and benefits for local people working on the projects listed above.

 

 

 

WEATHERIZATION

 

VILLAGE

NO/UNITS

SCOPE

STATUS

Kasigluk

18

Weatherization

Project Started

 

 

 

HEATHLY HOMES

 

This is in partnership with Alaska Native Tribal Health Consortium (ANTHC).

 

VILLAGE

NO/UNITS

SCOPE

STATUS

Emmonak and Alakanuk

22

Ventilation, safety devices, doors and windows

18 units complete